Day: October 10, 2017

SKI Project Report- September

STEP Contractor installed 19 tanks for the month. That brings the total tanks installed, as of 9-30-17, to 142. That equals about 23% of the contract amount paid to date with 21% of the contract time used. The contractor will be installing tanks on…