SKI Project Report- September

STEP

Contractor installed 19 tanks for the month. That brings the total tanks installed, as of 9-30-17, to 142. That equals about 23% of the contract amount paid to date with 21% of the contract time used. The contractor will be installing tanks on Utah next week. The contractor has indicated that they will be mobilizing an additional crew to start installing tanks. They will also be working on installing electrical disconnects on some of the sites that already have tanks installed. They will be contacting the homeowners of those sites before working on the outside electrical meters. County staff has received 588 easements to date. This is about 76% of all easements required.

Community

Contractor installed about 1500 lf of pipe by the open cut method this month. They have also installed 10 clean-outs for the month and connected several drill shots to open-cut pipes. This equates to about 67% of the contract paid out with 41% of the contract time used. Contractor will finish installing pipe in phase “C” and move to phase “B” to finish connection there.

Transmission

Contractor installed about 1050 lf of pipe by the open cut method this month. That makes about 76% of the contract paid out with 41% of the contract time used. This pipe is filling in some areas that were skipped over due to the extremely wet conditions at the time they were first there. It is also connecting some drill shots together.   Contractor will continue filling in these gaps heading south along RT 8 from Baltimore.

%d bloggers like this: