Project Update 09.29.17

STEP

This week six tanks were set on Tennessee and Utah. The contractor will continue on Utah and South Carolina next week. County staff has acquired 585 easements to date; this brings the total to 75% of the amount required.

Community

Contractor installed about 485 lf of pipe by the open cut method on Elm and South Carolina Roads. Contractor installed clean outs and fused the directional drilled pipe to the open cut line on Bay Drive.   Next week the contractor will continue to open cut on Tennessee Road.

Transmission

Contractor installed 60 lf of pipe South of Baltimore Road. The contractor will continue installing pipe South of Baltimore next week.