Month: October 2017

Project Update 10.27.17

STEP Contractor installed 9 tanks for the week on Utah Road, contractor will continue on Utah next week. County staff has acquired 603 easements and have conducted 221 pre-construction meetings to date. Community Contractor installed 233 lf and is continuing to install clean-outs and…

Project Update 10.20.17

STEP Contractor installed 6 tanks for the week on Utah Road. Contractor will continue on Utah next week. County staff has acquired 759 Right of Entries, 596 easements and have conducted 214 pre-construction meeting to date. Community Contractor is continuing to install clean-outs and…

Project Update 10.13.17

  STEP Contractor installed 5 tanks for the week on Utah Road, they will continue on Utah next week. We are still expecting to see the second tank crew sometime this month. County staff has acquired 759 right of entries, 592 easements and have…

SKI Project Report- September

STEP Contractor installed 19 tanks for the month. That brings the total tanks installed, as of 9-30-17, to 142. That equals about 23% of the contract amount paid to date with 21% of the contract time used. The contractor will be installing tanks on…