Project Update 10.13.17

 

STEP

Contractor installed 5 tanks for the week on Utah Road, they will continue on Utah next week. We are still expecting to see the second tank crew sometime this month. County staff has acquired 759 right of entries, 592 easements and have conducted 208 pre-construction meeting to date.

Community

Contractor is continuing to install clean-outs and make connection between open-cut pipe sections and direction drill section, they are currently working in the North Lake area.

Transmission

Contractor installed pipe between two drill shots from Baltimore Road heading south to the Porter farm. They installed a 50 foot stub on Chesapeake Estates Drive for the future phase. They will install the stub on Baltimore Road next week; that is also for the future phase.

 