STEP
Contractor installed 6 tanks for the week on Utah Road. Contractor will continue on Utah next week. County staff has acquired 759 Right of Entries, 596 easements and have conducted 214 pre-construction meeting to date.
Community
Contractor is continuing to install clean-outs and make connections between open-cut pipe sections and directional drill sections. Contractor is currently working in the North Lake and Virginia Road area. Next week contractor will complete North Lake and move to Utah Road.
Transmission
Contractor installed 42 lf of pipe completing the community main stub on Baltimore Drive. Contractor also installed and additional 96 lf of pipe north of the Porter Farm. **The Transmission main gaps are now filled in from the RT 50 Bore Shot to the South End of the Porter Farm*.