STEP
This week five tanks were set on Tennessee Road; contractor will continue on Tennessee next week. County staff has acquired 577 easements to date. That is about 74%
Community
Contractor installed about 150lf of pipe by the open cut method on Tennessee Road. Contractor also installed several clean-outs and made connections with open-cut and HDD pipe. Contractor also placed asphalt at several road crossings on County Roads. Contractor will continue with pipe connections next week.
Transmission
Contractor installed about 200lf of pipe by the open-cut method this week along Pier One Road. They also connected this to the HDD pipe that was previously installed, crossing RT50. Next week the contractor will back up to Baltimore Road to install some pipe and complete a tie-in in that area.