Project Update 09.15.17

STEP

Tennessee Road- The contractor set 4 tanks this week and will continue installing there next week. County staff has acquired 575 easements to date.

Community

The past week was spent filling the community main lines with water for pressure testing. The contractor was also installing clean-outs in Phase A and B. Contractor will continue installing pipe in Phase C next week.

Transmission

Contractor installed 340lf of pipe by the open cut method along Pier One Road; contractor will finish the connection to the RT 50 drill shot next week; will then move the open cut operation to Baltimore Road to connect the gap in that area.