STEP
The contractor installed 20 tanks for the month. That brings the total number of tanks installed to 123, or 16%. The contractor has used about 19% of the contractor time. County staff continues to acquire easements and answer questions at the SKI office. The SKI Office is now open Monday thru Friday, 7:30 am to 4:00 pm. Later hours can be accommodated by appointment only.
Community
The contractor installed 8700lf of pipe by the HDD and open-cut method for the month. That brings our total footage of pipe installed to 69,025lf. This is about 64% of the work to be completed with curb stops still needing to be installed. The contractor has used 37% of the contract time. The contractor has begun to fill the community main lines in phase A for pressure testing. Once the pressure test is completed, the contractor will start installing service connections in phase A.
Transmission
The contractor installed 900lf of pipe by the open-cut method for the month. That brings our total footage of pipe installed to 38,481lf. This is about 73% of the work to be completed. The contractor has used about 37% of the contract time. The contractor is currently working on Pier One Road. They are laying pipe to connect to the Drill shot that is currently under RT 50.