PROJECT UPDATE 08.28.17

16-01 STEP: 4 tanks were set this week on Oregon, South Carolina, and Elm Street. Contractor to continue on South Carolina and Oregon area.
16-02 Community: Contractor installed 1400 lf of pipe by the open cut and HDD method this week. Pipe was installed on Tennessee and Talbot Roads. Work will continue on Tennessee next week.
16-03 Transmission: Contractor installed 250 lf of pipe by the open cut method. This pipe was installed on the North Side of Pier One Road. Contractor will continue next week towards the RT 50 drill shot.