Project Update 11.10.2017

Step

Contractor installed 5 tanks for the week on Virginia and Bay Drive. County staff has acquired 622 easements to date and has held 236 pre-construction meetings with homeowners. The contractor will continue installing tanks on North Lake, Elm, and Virginia next week. The contractor has also established his staging area on Carroll Road

Community

The contractor installed about 350 lf of pipe by the open cut method. They continue to connect open cut pipe with HDD pipe.

Transmission

The contractor installed about 500 lf of pipe by the open cut method. This is filling in a gap that was located under the County trail and to wet to install last winter. They will continue working south to fill in any other gaps in the pipe.