STEP Contractor installed 5 tanks for the week on Utah Road totaling 173 Tanks set to date. Contractor will continue on Virginia and Bay Roads next week. County staff have acquired 80% (616) of 775 easements required . County staff has conducted 230 pre-construction meetings… Continue Reading “Project Update 11.03.17”