STEP
6 tanks were placed this week on Virginia Road; contractor will continue installing tanks on South Carolina next week. County staff have performed 258 pre-construction meetings with homeowners, and have acquired 640 (82%) easements to date.

Community
Contractor installed about 130lf of pipe to make connections and is installing division valves and clean-outs. This week the contractor is planning to start installing curb-stop valves on all the individual properties on Allegany Road next week.

Transmission
The contractor installed about 250lf of pipe to make connections on previously installed pipe. They also were paving along the trail and started some paving inside the communities. The contractor is planning on moving the open cut operation to North of RT 50 next week to complete that portion of pipe to the Sanitary District treatment plant.