Day: December 15, 2017

Project Update 12.15.17

STEP Contractor installed 6 tanks for the week on South Carolina. They plan to set tanks on Tennessee and North Lake next week. The contractor will also start installing service line pipe from the previously installed tanks to the street, next week on Touhey,…