Contractor set one tank this week on Worcester Road. They also started drilling service connections on Margaret Road. They will continue on Margaret Road next week.

Community

Contractor installed service connection on Ackerman Road. Will continue to finish up on Ackerman next week. 

Transmission

Contractor continues to work within the sewer treatment plant. They also connected pipe on South Carolina Road.

Weather put a damper on construction activity this week.

 