SKI Project Update 10.05.18

STEP Contractor installed 6 tanks on Bay Drive for the week. They also installed 5 electric meter replacements on Margaret Drive. The contractor installed 6 Bio tubes in previously installed tanks on Howard and Penny and installed about 720 lf of 1” service tubing… Continue Reading “SKI Project Update 10.05.18”