STEP
Contractor installed 6 tanks on Bay Drive for the week. They also installed 5 electric meter replacements on Margaret Drive. The contractor installed 6 Bio tubes in previously installed tanks on Howard and Penny and installed about 720 lf of 1” service tubing to those tanks. The contractor will continue installing tanks on Bay Drive next week. County staff have performed 419 pre-construction meetings and acquired 738 easements to date.
Community
Contractor started road patch restoration on Oregon Road. They will continue with road patching next week.
Transmission
Contractor completed the required stripping along the County Trail.