SKI Project Update 10.19.18

STEP Contractor installed 6 STEP tanks on Bay Drive for the week.  The contractor installed 05 electric meter replacement / modifications on Petinot and Touhey Drive this week.   The contractor also installed 12 Bio tubes in previously installed tanks on Long Point and Claiborne… Continue Reading “SKI Project Update 10.19.18”