STEP

Contractor installed 6 STEP tanks on Bay Drive for the week.  The contractor installed 05 electric meter replacement / modifications on Petinot and Touhey Drive this week.   The contractor also installed 12 Bio tubes in previously installed tanks on Long Point and Claiborne Roads, in addition to installing approximately 1,115 lf of 1″ service tubing to those tanks.  The contractor will continue installing tanks on Bay Drive next week.  County staff has performed 437 pre- construction meetings and acquired 739 easements to date.

Community

Contractor completed pavement patching restoration on Bay Drive, Utah and Tennessee Roads this week.  Next week, the contractor will work on roadside restoration.

 

Transmission

No activity

 