STEP
Contractor installed 3 tanks on Bay Drive for the week. The contractor installed 05 electric meter replacement / modifications on Petnoit and Margaret Drive this week. The contractor also installed 5 Bio tubes in previously installed tanks on Long Point Road and installed about 412 lf of 1″ service tubing to those tanks. The contractor will continue installing tanks on Bay Drive next week. County staff has performed 425 pre- construction meetings and acquired 738 easements to date.
Community
Contractor worked on pavement patching restoration on Utah Road, North Lake and Bay Drive. They will continue with road patching next week.
Transmission
No activity