Day: November 2, 2018

SKI project update 11.2.18

STEP Contractor installed 4 STEP tanks on Bay Drive for the week. The contractor installed 5 electric meter replacement / modifications on Maryland Road this week. The contractor also installed 6 bio tubes in previously installed tanks on Pennick Drive, in addition to installing…