STEP Contractor installed 4 STEP tanks on Tennessee, Oregon and Romancoke Roads for the week. Total STEP tank installs 417 to date. The contractor also installed 1 bio tube (less pump) this week to a previously installed tank on Harford Road, in addition to… Continue Reading “SKI Project Update 12.28.18”
16-01 STEP Contractor installed 3 STEP tanks on Tennessee and Oregon Roads for the week. The contractor installed 5 electric meter replacements / modifications on Elm Street and Maryland Road, this week. The contractor also installed 4 bio tubes (less pump) this week in… Continue Reading “SKI Project Update 12.21.18”
STEP Contractor installed 7 STEP tanks on Maryland, South Carolina and Oregon Roads for the week. The contractor installed 10 electric meter replacements / modifications on Maryland, this week. The contractor also installed 7 bio tubes (less pump) this week in previously installed tanks… Continue Reading “SKI Project Update 12.14.18”