Month: January 2019

SKI Project Update 1.25.19

STEP The contractor installed 2 STEP Tanks on N. Lake and Utah Road for the week.  This week the contractor installed 5 electric meter replacements / modifications on Oregon Road.  The contractor is working on completing two house connections to the Public Sewer System…

SKI Project Update 1.18.19

STEP The contractor installed 3 STEP Tanks on Elm Street and Tennessee Road for the week.  A total of 428 STEP Tanks have been installed to date.  This week the contractor installed 5 electric meter replacements / modifications on Oregon Road.   One control panel…

SKI Project Update 1.11.19

STEP Contractor installed 8 STEP tanks on Tennessee and Romancoke Roads, Oak and Elm Street during the first two weeks of January.   The contractor installed 6 electric meter replacements / modifications on Maryland and New Jersey Roads, Oak and Elm Street for the first…

SKI Project Update 1.4.19

STEP Not much progress this week; Merry Christmas and Happy New Year!