SKI Project Update 1.25.19

STEP

The contractor installed 2 STEP Tanks on N. Lake and Utah Road for the week.  This week the contractor installed 5 electric meter replacements / modifications on Oregon Road.  The contractor is working on completing two house connections to the Public Sewer System on Harford and Olive Brank Roads this week.  The contractor installed 1 BIO Tube less pump on Olive Branch Road, in addition to installing 84lf of 1” pressure service tubing to that tank. House connections and 1” drill shots will continue on Harford and Olive Branch Roads next week.  County staff has performed 511 pre- construction meetings and acquired 750 easements to date.