Month: February 2019

SKI Project Update 2.15.19

STEP Two rain days for the week:  One STEP Tank was installed on Queen Anne Road by the contractor this week.  The contractor also installed 5 electric meter replacements / modifications on Oregon Road.  The contractor completed one house connection to the Public Sewer…

SKI Project Update 2.8.19

STEP One STEP Tank was installed on Cecil Road by the contractor this week.  The contractor also installed 11 electric meter replacements / modifications on Oregon Road.  The contractor completed two house connections to the Public Sewer System on Cecil and North Lake Roads…

SKI Project Update 2.1.19

STEP The contractor installed 1 STEP Tank on N. Lake for the week.  This week, the contractor installed 3 electric meter replacements / modifications on Oregon Road.  The contractor completed four house connections to the Public Sewer System on Margaret Drive, Harford and Olive…