SKI Project Update 2.15.19

STEP

Two rain days for the week:  One STEP Tank was installed on Queen Anne Road by the contractor this week.  The contractor also installed 5 electric meter replacements / modifications on Oregon Road.  The contractor completed one house connection to the Public Sewer System on New Jersey Road and also currently working on one additional connection and startup on Queen Anne Road for the week.  The contractor installed 2 pumps in the BIO tubes, in addition to installing 26’ of gravity sewer line to the individual homes.  The contractor also completed 4 septic tank abandonments this week.  Next week, the contractor will continue with 1” drill shots and priority list house connections   County staff has performed 518 pre- construction meetings and acquired 750 easements to date.

 