SKI Project Update 2.1.19

STEP The contractor installed 1 STEP Tank on N. Lake for the week.  This week, the contractor installed 3 electric meter replacements / modifications on Oregon Road.  The contractor completed four house connections to the Public Sewer System on Margaret Drive, Harford and Olive…