SKI Project Update 2.8.19

STEP One STEP Tank was installed on Cecil Road by the contractor this week.  The contractor also installed 11 electric meter replacements / modifications on Oregon Road.  The contractor completed two house connections to the Public Sewer System on Cecil and North Lake Roads…