SKI Project Update 3.15.19

STEP This week including March 8th the contractor completed 5 house connections to the Public Sewer System on Maryland, Utah, Virginia, Queen Anne and Dorchester Roads.  Two STEP tanks were installed by the contractor this week on Queen Anne and Dorchester Roads.  The contractor…

SKI Project Update 3.8.19

STEP This week the contractor completed 2 house connections to the Public Sewer System on Maryland and Harford Roads and currently they are working on 2 additional house connections on Maryland and Utah Roads.  The contractor installed three STEP tanks on Utah and Virginia…

SKI Project Update 3.1.19

STEP This week the contractor completed 7 house connections to the Public Sewer System on Maryland and Olive Branch Roads.   The contractor installed 6 pumps to 6 previously installed BIO tubes and installed 1 BIO tube with pump in addition to installing 320LF of…