SKI Project Update 2.15.19

STEP Two rain days for the week:  One STEP Tank was installed on Queen Anne Road by the contractor this week.  The contractor also installed 5 electric meter replacements / modifications on Oregon Road.  The contractor completed one house connection to the Public Sewer…