STEP
The contractor installed 3 STEP Tanks on Elm Street and Tennessee Road for the week. A total of 428 STEP Tanks have been installed to date. This week the contractor installed 5 electric meter replacements / modifications on Oregon Road. One control panel was installed on Olive Branch Road by the contractor this week. The contractor completed two house connections to the public sewer system on Harford Road this week. The contractor drilled 169lf of electrical conduit from previously installed tanks to control panels and disconnects on Harford Road this week The contractor will continue installing STEP tanks on Tennessee Road next week. House connections will continue on Harford Road next week. County staff has performed 510 pre- construction meetings and acquired 748 easements to date.