STEP
Contractor installed 8 STEP tanks on Tennessee and Romancoke Roads, Oak and Elm Street during the first two weeks of January. The contractor installed 6 electric meter replacements / modifications on Maryland and New Jersey Roads, Oak and Elm Street for the first two weeks of January. The contractor also installed 5 BIO tubes (less pump) for the first two weeks of January to previously installed tanks on Harford and Olive Branch Roads, in addition to installing approximately 555lf of 1″ pressure service tubing to those tanks. Three Control Panels have been installed to date. The contractor will continue installing STEP tanks on Elm Street next week. House connections will begin on Harford next week. County staff has performed 506 pre- construction meetings and acquired 748 easements to date.