SKI Project Update 12.21.18

16-01 STEP

Contractor installed 3 STEP tanks on Tennessee and Oregon Roads for the week.  The contractor installed 5 electric meter replacements / modifications on Elm Street and Maryland Road, this week.   The contractor also installed 4 bio tubes (less pump) this week in previously installed tanks on Maryland Road, in addition to installing approximately 435lf of 1″ service tubing to those tanks.  One Control Panel install was completed by the contractor on Maryland Road this week. The contractor will continue 1” Drilling on New Jersey Road and installing STEP tanks on Oregon and Tennessee Roads next week.  County staff has performed 490 pre- construction meetings and acquired 746 easements to date.