STEP
Contractor installed 7 STEP tanks on Maryland, South Carolina and Oregon Roads for the week. The contractor installed 10 electric meter replacements / modifications on Maryland, this week. The contractor also installed 7 bio tubes (less pump) this week in previously installed tanks on Worcester and Caroline Roads, in addition to installing approximately 728lf of 1″ service tubing to those tanks. The contractor will continue installing STEP tanks on Oregon and South Carolina Roads next week. County staff has performed 486 pre- construction meetings and acquired 746 easements to date.
Community
Complete
Transmission
Complete