SKI Project Update 11.30.18

STEP

Contractor installed 14 STEP Tanks on Maryland and Oregon Roads for the weeks of 11.19 and 11.26.18.  The contractor installed 10 electric meter replacements / modifications on New Jersey, N. Lake, Cecil, Queen Anne, Dorchester Roads and Bay Drive for the week of 11.19.18.   The contractor also installed 9 bio tubes (less pump) for weeks of 11.19 and 11.26.18 in previously installed tanks on Baltimore, Romancoke, Kent and Dorchester Roads, in addition to installing approximately 815lf of 1″ service tubing to those tanks.  The contractor will continue installing STEP Tanks on Maryland, New Jersey and Oregon next week.  County staff has performed 474 pre- construction meetings and acquired 744 easements to date.

Community

This week and next week, the contractor continues to work on punch list throughout the community.

Transmission

Complete

 