SKI Project Update 11.16.18

STEP

Contractor installed 2 STEP tanks on Elm Street and Maryland Road for the week.  The contractor installed 5 electric meter replacements / modifications on Maryland and Wicomico Roads this week.   The contractor also installed 4 bio tubes (less pump) this week in previously installed tanks on Pennick Drive, Elm Street, Romancoke and Maryland Roads, in addition to installing approximately 351lf of 1″ service tubing to those tanks.  The contractor will continue installing STEP tanks on Maryland Road next week.  County staff has performed 464 pre- construction meetings and acquired 742 easements to date.

Community

This week and next week, the contractor will continue working on punch list throughout the community.

Transmission

Complete

 