Day: December 21, 2018

SKI Project Update 12.21.18

16-01 STEP Contractor installed 3 STEP tanks on Tennessee and Oregon Roads for the week.  The contractor installed 5 electric meter replacements / modifications on Elm Street and Maryland Road, this week.   The contractor also installed 4 bio tubes (less pump) this week in… Continue Reading “SKI Project Update 12.21.18”