STEP
Contractor installed 4 STEP tanks on Bay Drive for the week. The contractor installed 5 electric meter replacement / modifications on Maryland Road this week. The contractor also installed 6 bio tubes in previously installed tanks on Pennick Drive, in addition to installing approximately 651lf of 1″ service tubing to those tanks. The contractor will continue installing STEP tanks on Maryland Road next week. County staff has performed 461 pre- construction meetings and acquired 741 easements to date.

Community
This week the contractor worked on roadside restoration on the west side of Kent Island Estates. Next week, the contractor will continue working on punch list throughout the community.

Transmission
Complete

 