SKI Project Update 5.3.19

STEP

This week the contractor completed 4 house connections to the Public Sewer System on Maryland Road, Oak and Elm Street.  The contractor installed 2 STEP Tanks on Elm Street and Worcester Road.  Three STEP pump assemblies were installed to a previously installed BIO tubes and one BIO tube with a STEP pump assembly was installed in addition to installing 186LF of 4”gravity sewer line to the individual homes.  The contractor completed 5 septic tank abandonments during the week. One control panel was installed by the contractor along with 80LF of 1” electrical conduit and 33LF of 1” pressure sewer line drilling.   Ten electric meter replacements / modifications were installed by the contractor for the week on Bay Drive and Tennessee Road.  The contractor also worked on yard restorations throughout the Kent Island Estates Community.  Next week, the contractor will continue with 1” drill shots and priority list house connections.  The contractor will continue to post signs for upcoming house connection locations next.

  • County staff has performed 537 pre- construction meetings and acquired 754 easements to date.
  • County staff has performed 5 post-construction meetings to date.
  • The contractor has installed 451 STEP tanks to date.
  • The contractor has connected 61 houses to the public sewer system to date.

60d8a4ef-e745-47c8-8a0b-a901017c02a9    36639192-881e-4d35-a307-75a222f57eea

%d bloggers like this: