STEP This week the contractor completed 4 house connections to the Public Sewer System on New Jersey Road. The contractor installed 3 STEP tanks on Ackerman Drive, Talbot and Worester Roads. Four STEP pump assemblies were installed to previously installed BIO tubes in addition… Continue Reading “SKI Project Update 6.28.19”
STEP This week the contractor completed 5 house connections to the Public Sewer System on Bay Drive, Queen Anne and New Jersey Roads. The contractor installed 3 STEP tanks on Romancoke Road, Penny Lane and Ackerman Drive. Four STEP pump assemblies were installed to… Continue Reading “SKI Project Update 6.21.19”
STEP This week the contractor completed 4 house connections to the Public Sewer System on Bay Drive and North Lake Road. The contractor installed 3 STEP tanks on Howard, North Lake and Queen Anne Roads. Four STEP pump assemblies were installed to a previously… Continue Reading “SKI Project Update 6.14.19”
STEP This week the contractor completed 4 house connections to the Public Sewer System on Penny Lane, Claiborne, Oregon, and Maryland Roads. The contractor installed 1 STEP tank on Howard Road. Three STEP pump assemblies were installed to a previously installed BIO tubes and… Continue Reading “SKI Project Update 6.7.19”
16-01 STEP This week the contractor completed 3 house connections to the Public Sewer System on Elm Street, Ackerman Drive and Tennessee Road. The contractor installed 2 STEP tanks on Penny Lane and Baltimore Road. One STEP pump assembly was installed to a previously… Continue Reading “SKI Project update 5.31.19”