Month: May 2019

SKI Project Update 5.24.19

STEP This week the contractor completed 6 house connections to the Public Sewer System on Oak Street, Talbot, Cecil, Wicomico and Queen Anne Roads.  The contractor installed 1 STEP tank on Queen Anne Road.   Four STEP pump assemblies were installed to previously installed BIO… Continue Reading “SKI Project Update 5.24.19”

SKI Project Update 5.17.19

STEP This week the contractor completed 3 house connections to the Public Sewer System on Romancoke Road, Penny Lane and Pennick Drive.   The contractor installed 2 STEP tanks on North Lake and Oregon Roads.   Two STEP pump assemblies were installed to previously installed BIO… Continue Reading “SKI Project Update 5.17.19”

SKI Project Update 5.10.19

STEP This week the contractor completed 5 house connections to the Public Sewer System on New Jersey Road, Oak and Elm Street.  The contractor installed 1 STEP Tank on Romancoke Road.  Five STEP pump assemblies were installed to a previously installed BIO tubes in… Continue Reading “SKI Project Update 5.10.19”

SKI Project Update 5.3.19

STEP This week the contractor completed 4 house connections to the Public Sewer System on Maryland Road, Oak and Elm Street.  The contractor installed 2 STEP Tanks on Elm Street and Worcester Road.  Three STEP pump assemblies were installed to a previously installed BIO… Continue Reading “SKI Project Update 5.3.19”

SKI Project Presentation 4.27.19

Southern Kent Island Sewer Project Phase II Open House Below is the presentation which was displayed during the Phase II Open House on April 27th, 2019. This presentation helped to show the different aspects involved during the upgrade process while switching over to the… Continue Reading “SKI Project Presentation 4.27.19”