SKI Project Update 5.10.19

STEP

This week the contractor completed 5 house connections to the Public Sewer System on New Jersey Road, Oak and Elm Street.  The contractor installed 1 STEP Tank on Romancoke Road.  Five STEP pump assemblies were installed to a previously installed BIO tubes in addition to installing 199LF of 4”gravity sewer line to the individual homes.  The contractor completed 6 septic tank abandonments during the week.  Three control panels were installed by the contractor along with 768LF of 1” electrical conduit and 1” pressure sewer line drilling.   Ten electric meter replacements / modifications were installed by the contractor for the week on Elm Street, North Lake, Tennessee and Queen Anne Roads.  The contractor also worked on yard restorations throughout the Kent Island Estates Community.  Next week, the contractor will continue with 1” drill shots and priority list house connections.  The contractor will continue to post signs for upcoming house connection locations.

  • County staff has performed 538 pre- construction meetings and acquired 754 easements to date.
  • County staff has performed 5 post-construction meetings to date.
  • The contractor has installed 452 STEP tanks to date.The contractor has connected 66 houses to the public sewer system to date.
  • The contractor has connected 66 houses to the public sewer system to date.

 

8e4288c9-1bfd-417f-9fb3-7f49a37511d6f556e7ea-0937-4a62-9653-cac33ee9af87

 

 

%d bloggers like this: