SKI Project Update 8.2.19

STEP This week the contractor completed 4 house connections to the Public Sewer System on Allegany Road in addition to 138LF of 4” gravity sewer line to those individual homes.  The contractor completed 6 STEP tank installs on Allegany Road which included 4 STEP… Continue Reading “SKI Project Update 8.2.19”