SKI Project Update 8.2.19

STEP

This week the contractor completed 4 house connections to the Public Sewer System on Allegany Road in addition to 138LF of 4” gravity sewer line to those individual homes.  The contractor completed 6 STEP tank installs on Allegany Road which included 4 STEP assemblies with pump and 9 septic tank abandonments.  Four control panels were placed by the contractor along with the installation of 873LF of 1″ electrical conduit and 1″ pressure sewer line.   The contractor also completed 10 electric meter replacements / modifications for the week on Penny Lane, Somerset and Queen Anne Roads.  The contractor continues with daily yard stabilization and restorations.  Next week, the contractor will continue with 1″ drill shots, existing and priority list house connections.  The contractor will update road signs for upcoming house connection locations.  County staff has performed 576 pre- construction meetings and acquired 755 easements to date.

  • County staff has performed 5 post-construction meetings to date.
  • The contractor has installed 483 STEP tanks to date.
  • The contractor has connected 108 houses to the public sewer system to date.

aab2535f-0a7b-43d0-bcb1-f64056622bb42f245666-5d40-4eb8-a2a9-8a1b020ef8054b09c207-2480-42a1-a211-87489d79dee7

%d bloggers like this: