SKI Project Update 8.9.19

STEP

This week the contractor completed 8 house connections to the Public Sewer System on Allegany and Claiborne Road.  Eight STEP pump assemblies were installed to previously installed BIO tubes in addition to 301LF of 4” gravity sewer line installed to the individual homes.  The contractor completed 12 septic tank abandonments.  Five control panels were placed by the contractor along with the installation of 966LF of 1″ electrical conduit and 1″ pressure sewer line.   The contractor also completed 5 electric meter replacements / modifications for the week on Allegany, Queen Anne and Point Road.  The contractor continues with daily yard stabilizations and restorations.  Next week, the contractor will continue with 1″ drill shots, existing and priority list house connections.  The contractor will update road signs for upcoming house connection locations.  County staff has performed 584 pre- construction meetings and acquired 755 easements to date.

  • County staff has performed 5 post-construction meetings to date.
  • The contractor has installed 487 STEP tanks to date.
  • The contractor has connected 116 houses to the public sewer system to date.

 

cf4b554a-d6de-4980-bda0-ae060e2f0215

3a1b1b4a-9fde-4790-adc1-2be938bae4aa

%d bloggers like this: