STEP This week the contractor completed 9 house connections to the Public Sewer System on Queen Anne, Long Point and Petinot Road. One STEP tank was installed by the contractor this week on Queen Anne Road. Seven STEP assemblies with pumps were installed along… Continue Reading “SKI Project Update 9.27.19”
16-01 STEP This week the contractor completed all house connections on Touhey Drive; connecting 9 houses to the Public Sewer System. Two STEP tanks were installed by the contractor this week on Queen Anne Road. Nine STEP assemblies with pumps were installed in addition… Continue Reading “SKI Project Update 9.20.19”
The contractor completed house connections on Allegany Road this week. Contractor moved operation to Touhey, where they started house connections and 1” service line drilling. Contractor is working on restoration on Allegany. Contractor also replaced or modified 9 electric meters on Baltimore Road and… Continue Reading “SKI Project Update 09.13.19”
This week the contractor completed Allegany Road connections to the public sewer system. The Contractor will be moving to Touhey next week.. The contractor has installed 502 STEP tanks to date. The contractor has connected 133 existing houses to the public sewer system to… Continue Reading “SKI Project Update 09.06.19”