SKI Project Update 09.13.19

The contractor completed house connections on Allegany Road this week. Contractor moved operation to Touhey, where they started house connections and  1” service line drilling.

Contractor is working on restoration on Allegany.

Contractor also replaced or modified 9 electric meters on Baltimore Road and Romancoke Road this week.

Work will continue on Touhey for the next few weeks until all houses on Touhey have been connected.