Month: August 2019

SKI Project Update 8.23.19

16-01 This week the contractor completed 5 house connections to the Public Sewer System on Allegany Road.  Five STEP tanks were installed by the contractor this week on Allegany Road.  Three STEP pump assemblies were installed to previously installed BIO tubes and 2 STEP…

SKI Project Update 8.16.19

STEP This week the contractor completed 5 house connections to the Public Sewer System on Allegany and Oregon Road.  Five STEP tanks were installed by the contractor this week on Allegany Road.  Five STEP pump assemblies were installed to previously installed BIO tubes in…

SKI Project Update 8.9.19

STEP This week the contractor completed 8 house connections to the Public Sewer System on Allegany and Claiborne Road.  Eight STEP pump assemblies were installed to previously installed BIO tubes in addition to 301LF of 4” gravity sewer line installed to the individual homes. …

SKI Project Update 8.2.19

STEP This week the contractor completed 4 house connections to the Public Sewer System on Allegany Road in addition to 138LF of 4” gravity sewer line to those individual homes.  The contractor completed 6 STEP tank installs on Allegany Road which included 4 STEP…