SKI Project Update 7.26.19

STEP

This week the contractor completed 1 house connection to the Public Sewer System on Somerset Road in addition to 17LF of 4” gravity sewer line.  The contractor completed 4 STEP tank installs on Allegany Road.  The contractor completed 2 septic tank abandonments for the week.  One control panel was placed by the contractor along with the installation of 205LF of 1″ electrical conduit and 1″ pressure sewer line.  The contractor continues with daily yard restorations.  Next week, the contractor will continue with 1″ drill shots, existing and priority list house connections.  The contractor will update road signs for upcoming house connection locations.  County staff has performed 576 pre- construction meetings and acquired 755 easements to date.

  • County staff has performed 5 post-construction meetings to date.
  • The contractor has installed 477 STEP tanks to date.
  • The contractor has connected 104 houses to the public sewer system to date.

4633d8b1-b914-4e7b-acfe-87e4a59ef101

ad0e0c3f-e7af-4d6e-9e8c-4d2d3601f150

%d bloggers like this: