SKI Project Update 10.31.20

For the month of October 2020, the contractor completed 33 house connections to the Southern Kent Island public sewer system; those locations were Elm Street, Bay Drive, Talbot, Worcester, Caroline, Somerset and Utah Roads.  Eleven STEP tanks were installed on Bay Drive, Caroline, Somerset… Continue Reading “SKI Project Update 10.31.20”

SKI Project Update 9.30.20

16-01 STEP For the month of September 2020, the contractor completed 26 house connections to the Southern Kent Island public sewer system; those locations were Bay Drive, Beach, Somerset, South Carolina Talbot, Tennessee and Utah Roads.  Seventeen STEP tanks were installed on Beach, Somerset,… Continue Reading “SKI Project Update 9.30.20”